Taizhou Fourth Wastewater Treatment Plant Project
Project Name: General Contracting for the Purchase, Installation and Commissioning of Engineering Equipment of the Fourth Wastewater Treatment Plant of Taizhou City
Project Overview: The fourth sewage treatment plant is the environmental protection infrastructure project during the “Eleventh Five-Year Plan” period in Taizhou City. It is also an important supporting project for the national South-to-North Water Diversion Project to control pollution. The project is operated by the Golden State Environment in a BOT model (investment-construction-operation) with a franchise period of 30 years. The total scale of sewage treatment design is 80,000 tons/day, of which the first phase of the project is 40,000 tons/day, the first phase is 20,000 tons/day, and the total length of the sewage collection trunk network is about 18.45 kilometers.
Project scale: The total scale is 80,000 tons/day, of which the first phase of the project is 40,000 tons/day.
Service scope: general contracting for equipment procurement, installation and commissioning
Project Highlights: Representative BOT Wastewater Treatment Project